Oilers/Plant Tenders (HHC) Civil Service Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Oilers/Plant Tenders Test with comprehensive flashcards and multiple choice questions. Each question includes hints and explanations. Enhance your readiness for the exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


If 8 men can complete a repair job in 5 days, how long will it take 4 men working 10 hours a day to complete the same job?

  1. 4 days

  2. 5 days

  3. 6 days

  4. 10 days

The correct answer is: 6 days

To solve this problem, start with the initial data provided: 8 men can complete the job in 5 days. This means that the total amount of work required for the job can be represented in terms of man-days. Calculating the total man-days for the job involves multiplying the number of men by the number of days they work. In this case: 8 men × 5 days = 40 man-days. Now, if we consider the situation with 4 men working 10 hours a day, we need to determine their total man-days. Given that they work 10 hours a day, we can assume that 4 men working for 1 day would provide: 4 men × 1 day = 4 man-days for that day. To find out how many days it would take for these 4 men to complete the same workload as 40 man-days, we can set up the equation with the requirement of the job. Since they are producing 4 man-days per day, the number of days required to gather 40 man-days of work would be: 40 man-days ÷ 4 man-days per day = 10 days. Thus, it would take 4 men, working 10 hours a day, a